Monday, November 30, 2009

Exterior Wall in Readlyn


Because of the size of the site in Readlyn--we don't have a lot of extra space to work with--the exterior walls of the northeast corner of the building haven't been completed because it has allowed for easier access to the building for other parts of the project. With much of the floor poured, and the roof continuing to go on, the time has come for work to begin on that section of exterior block bearing wall. The foundations have been poured, and now, as you drive by, you'll see the block being laid. It won't be long and the building will be nearly completely enclosed. The steel is on the roof in the gymnasium, and the rubber roofing has been installed on a good portion of the main section of the building. The attached picture shows the newly laid block.